Introduction
As I wrote in my last article about tailoring, it’s all about making choices! What do I have to do to be successful. This article I will getinto tailoring PRINCE2 to fit for projects within a programme and large projects versus small projects.
a
As was indicated earlier, one programme recognizes one or more projects and a number of activities. Think, for example, of an organization that is starting up a warehouse as a programme, where all kinds of projects are necessary to bring about its utilization. The aim of the programme is then formulated in terms of profits, stocks, number of customers (per time unit), etc. Examples of projects could be: the organization of the shop, constructing the parking bays, hiring of staff, etc. Nevertheless activities are still required to enable development and to realize benefits , such as the buying and selling of products.
a
With the tailoring of a project as a part of a programme, a few aspects are adapted: themes, processes and management products. For the programme management aspects reference is made to ‘Managing Successful Programmes’ (MSP) from the OGC.
a
With Starting up a Project within a programme there will usually be a good overview in place of what must happen in outline. The project mandate will mainly contain the information that is necessary to enable a Project Brief . Sometimes the complete Project Brief has already been delivered by the programmes. However, this Project Brief must not simply be accepted. It remains important to check again every time whether the delivered particulars are consistent and realistic. That is the responsibility of the Project Manager .
a
The Business Case of the project is defined on the basis of the standards of the programme. Sometimes the Business Case is provided by the programme or it can be a reduced level of content. The responsibility for realizing and monitoring the benefits of the project lies with the programme. The Benefits Review of the project can be a part of the benefits realization plan of the programme.
a
The organization structure is about an optimal connection being created between the programme and project organization for an efficient manner of reporting and reviewing. Often the role of Executive will be filled by the programme manager or a direct delegate. In this way coordinated Project Support and Project Assurance is also organized in most cases. This helps enormously with communication in the programme and across projects. In this way the underlying projects will get the necessary information of the programmes much more directly. And vice versa, with information about, for example, a project experiencing scope creep reaching other parties involved in the programme more seamlessly.
a
Another example of the possible integration of roles is that the change manager(s) in the programme can fill the role of Senior User(s) in the project. The design authority, or the architect of the programme, can also fill the role of Project Assurance or Change Authority in the project (see figure 1). What is important is that there is a clear division of responsibilities and that overlap is prevented.
Figure 1. Project and Programme management roles
(Source: Project management based on PRINCE2)
With any project that exceeds the planned level of change, coordination with programme management must take place and, where necessary, programme management will have to take decisions. Here one can for example think of not only changing of the objectives, but also changing the Business Case.
a
Another aspect is that the programme can supply the Quality Management Strategy for the project. In this way the programme can give advice about quality methods and provide help with the execution of quality control and quality assurance activities. With the planning of the project, care must be taken that the standards of the programme monitoring and control are followed. In the Project Plan dependencies with other projects within the programme must be covered.
a
When determining a project’s strategies, the strategies of the programme should form the starting point. It also has consequences for the techniques and classifications to be used, in the project. The issue solution strategy of the programme is used as a guideline for the issue and change procedures of the project.
a
The information management strategy of the programme will be a guideline for the Configuration Management Strategy of the project. In the same way the monitoring and control strategy of the programme is a guideline for reporting and monitoring activities of the project. In addition the programme determines the project tolerances and the number and length of the stages.
Scale of the project
The scale of a project doesn’t only relate to its size, but also the complexity, the risk and the importance of the project. For all PRINCE2 principles it must be established how they can be used instead of not using certain principles. The use of PRINCE2 can be regarded as the reduction of project failure. If an element of PRINCE2 is taken less seriously, it must be regarded as a risk.
Table 1. Examples of projects of different scales
(Source: Project management based on PRINCE2)
Large versus small projects
Medium-sized and large projects recognize several delivery stages in addition to the initiation stage. With short-running, non-complex projects with limited risks, the project may only consist of two management stages: the initiation stage and the delivery stage. With small and straightforward projects the Starting up a Project and Initiating a Project processes are sometimes combined (see figure 2).
a
In such cases the two processes can be informally dealt with together in a single discussion. It is advisable in such instances to record the decisions in a discussion memo. For example this could be possible where the project involves a small internal move within one department or something similar.
For small projects the Controlling a Stage process can be summarized in the following activities:
- Allocating work to be executed;
- Monitoring the progress;
- Ensuring that the agreed quality is realized;
- Ensuring that changes are carried out after approval;
- Monitoring risks;
- Reporting the progress of the work;
- Keeping a watchful eye for changes occurring to the plan.
a
These activities must be carried out even in the smallest projects. The question is, however, whether reporting on these activities must always be done by means of bulky reports. In small and informal projects quite simple reports are adequate, or reporting can even be done verbally or via e-mail. However, the project management team must realize that verbal reports have inherent risks. An argument may develop about what had been agreed. And what happens if the Project Manager is temporarily unavailable or leaves the organization? The other themes can also be completed in a simpler manner, which results in smaller overheads.
Figure 2. Phasing projects
(Source: Project management based on PRINCE2)
For smaller projects and for those projects with only one team that reports directly to the Project Manager, the coordination between the Project Manager and the Team Manager can also be less formal. The Project Manager and the Team Manager may be one and the same person. The work of the Team Manager can be summarized as:
- Setting up agreements on work that must be done;
- Planning the work;
- Supervising the execution;
- Keeping an eye on the progress;
- Reporting the progress;
- Having the product s tested;
- Recording the results;
- Keeping up with the changes;
- Ensuring that the products are checked;
- Delivering the products to the Project Manager.
The role of Project Support can also be undertaken by the Project Manager.
a
For small projects the Closing a Stage process can be summarized in the following activities:
- Checking whether everything has been delivered and accepted;
- Checking that there are no loose ends;
- Recording outstanding points;
- Archiving the project file for later assessments;
- Signing off people and resources.
Small projects and bureaucracy
Sometimes small projects are choked by too much paper and bureaucracy. Most procedures and templates in organization s that are developed to organize and manage projects, are based on large and complex projects. For organizations that have ISO certification, it is applicable for management and specialist activities to be thoroughly undertaken. That requires additional paper work and the accompanying signatures. This is not a PRINCE2 requirement, however.
a
PRINCE2 can reinforce all of this because the method is complete and is underpinned by a large number of templates. All available PRINCE2 templates are often also used to guarantee a feeling of maximum control over the project. The result is an overkill of documents. This can detract attention from what is really important and can create an aversion to all documents, including instances when a document is in fact important. An overkill of documents in any case costs a lot of time and attention to produce and study. This time and attention can often be better spent on other matters.
a
All PRINCE2 processes must be adhered to in every project. However, the question is whether all processes in a given project are so important that specific procedures and templates for the execution of these processes are necessary. It is important to use only those procedures and templates in a project that are really important in the given circumstances and provide added value for organizing and managing that project. For small projects certain processes can be gone through and completed quickly and informally.
Project Manager versus Team Manager
Small projects typically use one project team. Only members of the project team itself work on the project, reporting directly to the Project Manager. In addition two situations can arise:
- Separate Work Package es are to be differentiated, but these Work Packages are still undertaken by one person. This person is then simultaneously a member of the team and Team Manager. In such a case the Project Manager and the Team Manager are separate people.
- The Project Manager does not direct the team member at the level of Work Packages, but at the level of activities. That is also the case if the team member is not yet sufficiently senior to execute the Work Package independently and the Project Manager has sufficient subject content expertise about the work area to be executed. In such a case the Project Manager and Team Manager are one and the same person.
In small projects both situations can occur simultaneously. The second option, however, has the inherent danger that the team member concerned feels insufficiently involved and will sit back, “The Project Manager tells me what to do anyway. It is their project/problem and not my project/problem.” This develops especially when a team member (in their own estimation) has sufficient expertise to function as Team Manager, but is not given this responsibility. This is not good for team building and commitment in the team and only reinforces the risk that the Project Manager will still interfere with the content. Too often the Project Manager strongly interferes ‘out of habit’ with the content of the activities. It could be that the Project Manager is not used to directing on the basis of Work Packages and remains stuck in the old procedure. Coaching by a senior Project Manager is then necessary to avoid similar situations.
Large projects
There is essentially no difference between a ‘small’ and a ‘large’ project. A product or service still has to be delivered. A large project, however, is regarded as a project with several project parts where each is directed as a project, for example with its own Executive , Project Board and Project Manager. A Project Board that coordinates all the different Project Boards is responsible for the entire project. The building of the space shuttle is a huge project, just like the building of the Channel Tunnel. However, the result that is delivered is nonetheless still a product. It is for the customer to use the product and to realize their objectives with it. So, it remains a project and not a programme .
a
The difference between a portfolio of projects and a large project is that in a portfolio of projects the different projects sometimes deliver several results, sometimes solitary and sometimes in clusters, with each being capable of delivering added value for an organization; with a large project, one inextricably bound total result is delivered.
a
With a large project one can naturally use the same methods and techniques as with multi project management and with managing a portfolio of projects, and these techniques are found again in the management of programmes.
Finally
In the next article I will go into tailoring PRINCE2 for different kinds of projects and in different context. All kinds of projects have their own characteristics and possibilities to tailor it towards success!
a
Please feel free to comment on my articles. I’d love to get into remarks and questions.
For any other information, please mail me (gabor.visvanheemst@intrprimus.nl).